Keep the motor dry and clean.
Store within the temperature range ( -20°C - +40°C ).
Energise heaters if fitted, or use desiccant.
Rotate the shaft weekly.
Every 3 months, check the insulation resistance. If less than 10dry out.

  MECHANICAL INSTALLATION
  Lifting
Always use correct lifting facilities.
Note: Maximum hand lift is 20kg below shoulder, and above ground level.
The eyebolts are to support the motor only.
Eyebolts are designed for vertical lifting
Ensure a level mounting surface.
Ensure a correct fastner torques.
Ensure gaskets, seal and guards are correctly fitted.
Ensure adequate ventilation and space for maintenance.


Before working on a machine, ensure that it is switched off, and the power source is isolated.
Check insulation resistance of all windings with 500V dc Megger. If less than 10 dry out.
Check overload setting.
Heaters, if fitted, will be live when the motor is stationary.
Mains cables must be correctly sized.
Check terminal arrangements; Tight connection; Driven equipment is free; And rotation (uncoupled).
Terminal box lids must be fitted after connection and testing.


  MAINTENANCE AND SPARE PARTS
Remember to isolate power source before any maintance.
Periodic maintenance should be done every 2000 running hours, or every 3 months.
  e.g. check for visible damage, such as cracked fans, covers, feet, frames etc.
Clean free of dust, dirt, fibres etc, from motor frame and fan cover.
Secure fastners, cables and earth leads.
Replace bearings every 3 years.
Never hammer a bearings. Always use an extractor.
Avoid damaging windings, when removing a rotor.